Update!
We have permit in hand. Pad clearing will occur either this weekend or early next week. The truss manufacturer is 10 weeks out. We ordered temp power pole and lined up foundation/slab, block layers for April. We need to pass 95% compaction before forms can be set. Once those are set plumber can do rough in. We then set steel, inbeds, vapor barrier, termite treat.
More to come....
We have permit in hand. Pad clearing will occur either this weekend or early next week. The truss manufacturer is 10 weeks out. We ordered temp power pole and lined up foundation/slab, block layers for April. We need to pass 95% compaction before forms can be set. Once those are set plumber can do rough in. We then set steel, inbeds, vapor barrier, termite treat.