I'm dealing with a situation that isn't working quite right, and need some advice on what is needed to correct it.
We have two Weil-McLain hot water boiler units heating a facility. The original system was forced air electric heat (installed in '78). When the cost of electric heat became an issue, the system was "converted" over to hot water heat. This same system also provides air conditioning.
The boilers have been incorporated into the original forced air system. A grid of copper tubing has been built and the boilers circulate hot water through the tubing. The blower fan passes air over the grid, creating hot air, which is used to heat the facility.
Yep... it's a little bit of a kludge.
Still with me?
Here's where the problems begin. The two boilers keep the water hot all the time... even when there's no call for heat. They sit and cycle 24 hours a day... high limit, off... low limit, on.
When the thermostat calls for heat, the blower kicks on, heats the room, and then the blower shuts off. However, the boilers continue to cycle. They're always ready to go. They're also using a lot of extra natural gas, that is being used to heat water when it isn't needed.
What I would like to see, is when the thermostat calls for heat, that it kicks on the boilers, allows them 5 minutes to heat the water (or a temperature sensor that can determine when the water reaches a set temperature), and *then* kick on the blower fan. When the thermostat reaches the set temperature, then it shuts down the fan AND the boilers.
Is it possible to get that five minute delay (or a temperature sensor) worked into the system, instead of having the boilers keeping the water hot all of the time? What would it take to incorporate a fix like this?
We have two Weil-McLain hot water boiler units heating a facility. The original system was forced air electric heat (installed in '78). When the cost of electric heat became an issue, the system was "converted" over to hot water heat. This same system also provides air conditioning.
The boilers have been incorporated into the original forced air system. A grid of copper tubing has been built and the boilers circulate hot water through the tubing. The blower fan passes air over the grid, creating hot air, which is used to heat the facility.
Yep... it's a little bit of a kludge.
Still with me?
Here's where the problems begin. The two boilers keep the water hot all the time... even when there's no call for heat. They sit and cycle 24 hours a day... high limit, off... low limit, on.
When the thermostat calls for heat, the blower kicks on, heats the room, and then the blower shuts off. However, the boilers continue to cycle. They're always ready to go. They're also using a lot of extra natural gas, that is being used to heat water when it isn't needed.
What I would like to see, is when the thermostat calls for heat, that it kicks on the boilers, allows them 5 minutes to heat the water (or a temperature sensor that can determine when the water reaches a set temperature), and *then* kick on the blower fan. When the thermostat reaches the set temperature, then it shuts down the fan AND the boilers.
Is it possible to get that five minute delay (or a temperature sensor) worked into the system, instead of having the boilers keeping the water hot all of the time? What would it take to incorporate a fix like this?