OVERKILL
$100 Site Donor 2021
In 2001 Ontario Power Generation built its first, and it turns out, only, wind turbine on the shores of Lake Ontario, directly next to the 4,000MW (3,048MW operational) Pickering Nuclear Power plant, which was constructed started in 1966 and grid connected in 1971. The single Vestas V80 unit, at 1.8MW, has had some reliability issues over its operating life and is the ONLY wind turbine in the province to be paid a market rate, since it's publicly owned.
https://www.opg.com/news/pickering-wind-turbine-to-be-removed/
In 2002, Ontario's first Commercial wind farm was installed in Bruce County, located directly behind the Juggernaut, Bruce Nuclear. This farm consists of 5 of the same Vestas V80 turbines, which will likely meet the same fate as the Pickering one next year.
Ontario's Green Energy Act has been dismantled, hundreds of contracts eliminated for new builds, so as it stands, there will be likely no new wind power constructed in the province in the near future, and none under the now dead GEA.
The Bruce site represents the peak of Nuclear in Canada. It was built before costs went crazy, and many lessons were learned from Pickering. It was the first series of 480 fuel channel CANDU units, which culminated as the CANDU 9 units that were built at Darlington. At 900MWe nominal (880MWe actual) this was as large as the CANDU would ever get. The units at Bruce, which were 750MWe (A) and 800MWe (B) have been uprated several times and now produce 779MWe and 817MWe, pending further uprates as the refurbishment commences.
The 18 year lifespan of these Vestas units marks the beginning of the end for contracted wind in Ontario. As these units reach EOL they will be removed and likely not replaced, given the lack of financial incentives now and the overall poor performance of wind generation in the province. The sun will have risen, and set, on GEA wind during the tenure of Bruce and Darlington, whose anticipated lifespan, barring further life extension and refurbishment, runs through to the mid 2060's.
https://www.opg.com/news/pickering-wind-turbine-to-be-removed/
In 2002, Ontario's first Commercial wind farm was installed in Bruce County, located directly behind the Juggernaut, Bruce Nuclear. This farm consists of 5 of the same Vestas V80 turbines, which will likely meet the same fate as the Pickering one next year.
Ontario's Green Energy Act has been dismantled, hundreds of contracts eliminated for new builds, so as it stands, there will be likely no new wind power constructed in the province in the near future, and none under the now dead GEA.
The Bruce site represents the peak of Nuclear in Canada. It was built before costs went crazy, and many lessons were learned from Pickering. It was the first series of 480 fuel channel CANDU units, which culminated as the CANDU 9 units that were built at Darlington. At 900MWe nominal (880MWe actual) this was as large as the CANDU would ever get. The units at Bruce, which were 750MWe (A) and 800MWe (B) have been uprated several times and now produce 779MWe and 817MWe, pending further uprates as the refurbishment commences.
The 18 year lifespan of these Vestas units marks the beginning of the end for contracted wind in Ontario. As these units reach EOL they will be removed and likely not replaced, given the lack of financial incentives now and the overall poor performance of wind generation in the province. The sun will have risen, and set, on GEA wind during the tenure of Bruce and Darlington, whose anticipated lifespan, barring further life extension and refurbishment, runs through to the mid 2060's.