Deck Piling Fail

Status
Not open for further replies.
All you have to do is put a larger tube over that mess, back fill and pour it again. Leave the bar its worthless and a PITA to get out, cut that old tube lower, and put a larger 12 or 10 over it. Back fill, level, and pour it.

Your deck is heaving because your tubes are not deep enough, since you have cold winters with deep frost I'd go down 6-8ft.

FYI in the future skip the bar on tubes, leave that to the bridge guys.
 
Last edited:
The other tube can slide into the first tube. The rebar should help hold together.

b4xd6u.jpg
 
Originally Posted By: Clevy
Looks good.


Just pour up to that point and you're stylin.



See. It could have been worse.

Where's the beers smily
Here ya go
10.gif
 
Originally Posted By: Nick1994
Originally Posted By: Clevy
Looks good.


Just pour up to that point and you're stylin.



See. It could have been worse.

Where's the beers smily
Here ya go
10.gif




Thanks
 
Poured, backfilled. Will remove jacks in 2-3 days, as we will get some rain for the next two.

Good learning experience,
 